Implementation & Delivery Plan
Delivery phases, sprint structure, team & RACI, environments, data migration, cutover, risks and the go-live runbook for Engagement & Loyalty Platform.
Delivery Approach
Agile delivery (2-week sprints) within a six-phase programme. Each phase ends with a demonstrable increment and a quality gate. Releases map to the PRD release plan (R1 Core → R4 Fund & optimise).
The engagement layer (event-trigger ingestion, trigger rules, milestones and scratch cards — SRS module M13) is delivered on top of the accrual/ledger core: it depends on the ledger being live (Phase 1) and lands alongside the campaign & milestone engine, with the the Bank's mobile app sample app demonstrating the end-to-end journey.
Six-Phase Roadmap
| # | Phase | Key outcomes | Exit gate |
|---|---|---|---|
| 1 | Discovery & Integration Design | Confirm requirements, interface specs (CBS, switch, channels, gateways), security design authority sign-off. | Signed-off design & interface contracts. |
| 2 | Core Accrual + Ledger Setup | Ingestion, accrual engine, loyalty ledger, base admin, MIS foundation (R1). | Accrual + ledger demo; integrity verified. |
| 3 | Campaign & Milestone Engine | Rule builder, campaigns, milestones, segments, communication (R2). | End-to-end campaign demo. |
| 4 | Redemption Catalogue Integration | Catalogue, redemption, fulfilment, customer surfaces (R3). | Redemption journey across channels. |
| 5 | UAT + Pilot Campaign | Business UAT, controlled pilot on a card segment, fixes. | UAT sign-off; pilot success criteria met. |
| 6 | Full Rollout + Optimization | Production rollout, merchant-funded, personalisation, tuning (R4). | Go-live; hypercare complete. |
Per-Phase Module Deliverables
Module-level deliverables mapped to phases (see CR-DCL-014 for build checklists and exit criteria). Cross-cutting items (security, audit, observability) run throughout.
| Phase | Modules & deliverables | Integration milestone |
|---|---|---|
| 1 · Discovery & Design | Interface specs, data contracts, security/signature design, threat model; schema (CR-DBS-013) baselined. | CBS/switch & channel contracts signed; signing-key (Vault/KMS) design agreed. |
| 2 · Accrual + Ledger | M3 Ledger (immutable entries, balance projection, FIFO lots); M1 Accrual engine (all earn types, versioned rules); M7 base Admin/RBAC + maker-checker; M8 MIS foundation (report_definition, audit_log, recon). | CBS/switch transaction feed live in SIT; integration_log wired. |
| 3 · Campaign & Milestone | M2 Campaign engine (all 11 types, segments, simulation, budget auto-pause); M10 Tiers & status; M6 Communication (templates, consent, triggers). | Notification gateways (SMS/Email/Push/WhatsApp) integrated; delivery webhooks. |
| 4 · Redemption & Catalogue | M4 Redemption & fulfilment (all methods, points+cash, signature-verified redemption, signed partner fulfilment); M9 Customer experience surfaces; M11 Integrity & risk (clawback, disputes). | Catalogue/voucher/gateway partner adapters integrated & signature-verified. |
| 5 · UAT + Pilot | Business UAT across all delivered modules; controlled pilot on a card segment; defect fixes & hardening. | End-to-end integration test across CBS, channels, comms & reward partners. |
| 6 · Rollout + Optimization | M5 Merchant-funded & settlement; M12 Transfer/pooling/partners/referral/gamification; personalisation & tuning; full MIS suite. | Merchant-funded settlement & partner-programme transfer integrations live. |
Indicative Schedule
Compressed 6-month plan: parallelised, overlapping agile delivery with UAT commencing in Month 4 and go-live in Month 6. Bars indicate active months (actual dates confirmed in mobilisation).
| Phase \ Month | M1 | M2 | M3 | M4 | M5 | M6 |
|---|---|---|---|---|---|---|
| 1 · Discovery & Design | ● | |||||
| 2 · Accrual + Ledger | ● | ● | ||||
| 3 · Campaign & Milestone | ● | ● | ||||
| 4 · Redemption & Catalogue | ● | ● | ||||
| 5 · UAT + Pilot | ● | ● | ||||
| 6 · Rollout + Go-live | ● | ● |
Sprint Structure
- 2-week sprints; ceremonies: planning, daily stand-up, review/demo, retrospective.
- Definition of Ready & Done enforced; stories trace to SRS & test cases.
- Continuous integration with automated tests; demoable increment each sprint.
- Hardening sprint before each major release for performance, security & regression.
Team Structure & RACI
| Activity | the Bank Business | the Bank IT/Sec | Cheggout Eng | Cheggout PM |
|---|---|---|---|---|
| Requirements & sign-off | A | C | R | C |
| Architecture & security design | C | A | R | C |
| Build & unit/integration test | I | C | A/R | C |
| Integration with CBS/channels | C | A/R | R | C |
| UAT execution | A/R | C | C | R |
| Security testing | I | A | R | C |
| Go-live approval | A | A | C | R |
| Hypercare & support | C | C | A/R | R |
R = Responsible · A = Accountable · C = Consulted · I = Informed
Data Migration & Onboarding
- Establish data feeds (transactions, card/customer master) from CBS/switch; validate schemas & control totals.
- Load opening point balances (if any legacy programme) via a one-time migration with reconciliation against source.
- Tokenise identifiers at ingestion; verify no raw PII persists.
- Backfill a defined historical window for campaign baselining (configurable).
- Dual-run / parallel reconciliation before cutover.
Cutover & Go-Live Runbook
| # | Step | Owner | Rollback |
|---|---|---|---|
| 1 | Freeze config; final UAT sign-off; backup baseline. | PM / the Bank | — |
| 2 | Deploy release to PROD (blue-green). | Cheggout Eng | Switch back to blue. |
| 3 | Enable feeds; smoke test accrual & balance. | Eng / IT | Disable feeds. |
| 4 | Activate pilot segment & first campaign. | the Bank Business | Pause campaign. |
| 5 | Verify notifications & redemption on pilot. | QA / Business | Disable channel. |
| 6 | Reconcile day-1; monitor dashboards. | Finance / SRE | Investigate exceptions. |
| 7 | Ramp to full population; exit to hypercare. | PM | Throttle ramp. |
Hypercare & Support Model
- 2–4 weeks intensive hypercare post go-live with daily triage & dashboards.
- Defect SLAs per Test Plan severity matrix.
- Transition to steady-state support (L1/L2/L3) with agreed SLAs & on-call.
- Quarterly optimisation: rule tuning, catalogue refresh, campaign performance review.
Programme Risks
| Risk | Likelihood | Impact | Mitigation / owner |
|---|---|---|---|
| Interface readiness (CBS/switch) | Medium | High | Early design, sandbox feeds, contract tests · the Bank IT. |
| Data quality in feeds | Medium | Medium | Validation, control totals, exception workflow · Eng. |
| Scope creep | Medium | Medium | Change control, phased releases · PM. |
| Security sign-off delays | Medium | High | Engage design authority in Phase 1 · the Bank Sec. |
| Reward liability surprises | Low | High | Budgets, caps, real-time liability MIS · Finance. |
| Adoption / awareness | Medium | Medium | Multi-channel comms, in-app surfacing · Business. |